Who approves a contingency draw, and who should

Jul 3, 20264 minute readBy Reltic VDC

A contingency draw is a decision. Somebody looks at a cost, decides it belongs to the contingency rather than to a change order or to the contractor's own fee, and moves the money. The question of who gets to make that decision is answered in the contract, and the answer is often not what the owner assumes.

The default in most agreements

Under most AIA A133 based agreements, the contractor's contingency is available to the construction manager for costs that are properly reimbursable but were not anticipated in detail. The contract typically requires the contractor to notify the owner and the architect when it draws, and sometimes to get approval. The exact language varies by project and by how hard the owner's counsel negotiated.

Owner contingency works differently. It is not in the contractor's hands at all. A draw from it is a change order, and a change order needs the owner's signature. So the approval question for owner contingency is really a question about the owner's own internal authority: who in the organization signs, and above what amount does it go to a committee or a board.

Two funds, two approval paths. The contractor's fund leans toward contractor control with owner visibility. The owner's fund leans toward owner control with contractor input. Check your contract for the specific wording, because the detail is what matters.

Three approval models owners actually use

In practice the contractor's contingency tends to run on one of three models. The first is notice only: the contractor draws, tells the owner, and moves on. The second is notice with a threshold: draws below a set dollar amount are notice only, draws above it require owner consent. The third is consent on everything, which is rare on large projects because it slows the work.

Each model trades speed for control. Notice only keeps the job moving and keeps the owner informed after the fact. Consent on everything gives the owner a veto but turns every field decision into a paperwork cycle. The threshold model is the usual compromise, and the threshold itself is the negotiated number.

Where the threshold model goes wrong

A threshold only works if someone is watching for draws that split into pieces to stay under it. Consider a fictional $18 million middle school addition with a $25,000 consent threshold. Four related draws of $22,000 each for the same roofing issue would each pass without consent. Together they are an $88,000 decision the owner never reviewed. The contract may not forbid this. The owner's log should at least show it.

Who should approve, regardless of the contract

Whatever the contract says about consent, the owner should treat every draw as something to review. Reviewing is not approving. It means reading the reason given, checking it against the cause categories the owner tracks, and asking whether the cost really belongs in the fund it landed in.

That review should sit with whoever holds the owner's ledger, often the owner's representative or a project accountant. On public owners it may be a facilities director who reports to a board. The person does not need authority to block a draw. They need the authority to raise a flag and to record a disagreement.

A recorded disagreement matters at closeout. If a draw was classified as contractor contingency in month four and the owner believed it was really a design gap, that note is the start of a recovery conversation with the design team later. Without the note, the moment passes.

Building the approval record

Every draw should carry four things in the owner's record: who requested it, who approved it and under which clause, what the stated cause was, and whether the owner agreed with that cause. The fourth field is the one most owners skip, and it is the one that pays off.

Costwitness records each draw with an approver, a cause, and an owner position, and it flags draws that exceed a threshold or arrive in clusters. It does not decide who was right. It makes sure the question was asked while the answer still mattered.

Steps for the next four weeks

  1. Read the contingency clause in your agreement and write down, in one sentence, who approves a contractor contingency draw and at what threshold.
  2. Confirm who on the owner's side has authority to sign a change order against owner contingency and at what amount it escalates.
  3. Go back through draws to date and mark any cluster of related draws that together exceed the consent threshold.
  4. Name one person responsible for reviewing every draw and recording the owner's view of its cause.

Questions on this

Can the owner refuse a contractor contingency draw?

Only if the contract gives the owner a consent right for that draw. Under a notice only arrangement the owner can question the draw and dispute the cause but cannot block it. Under a consent arrangement the owner can withhold approval. Check your contract for which applies and at what amount.

What if the architect is the one approving draws?

Some agreements route contingency notices through the architect as the owner's agent. That gives the owner a technical review but not a financial one. The owner should still keep its own record of each draw and its own view of the cause, because the architect is not tracking the owner's budget.

Should the owner's representative approve draws?

An owner's representative usually reviews and recommends rather than approves. The signing authority stays with the owner's organization. What the representative should hold is the record: every draw, every cause, and every point where the owner disagreed.

In the product

Contingency ledger, Change order register, Monthly owner report. Free tool: Contingency Runway, Pre-GMP Readiness Score.

Keep reading

Earlier: Contingency burn rate: how to read it against percent complete. Later: Contractor contingency versus owner contingency: two funds, two purposes. All articles on contingency.

One next step

See the two funds on a project like yours.

Thirty minutes on a call. The twin drawdown chart on a fictional project at your GMP size, and the month the fund runs out.

Request a demo