For owners on a GMP contract

The contractor's contingency runs out in month 13. The building is 41 percent built.

Nobody told the owner, because the only ledger on the contract belongs to the contractor. Costwitness keeps the owner's own.

The situation

You signed a price cap. Underneath it sit two funds for the unexpected.

A guaranteed maximum price is a ceiling, not a bill. Below the ceiling sits the contractor's contingency, carried inside the GMP to absorb what the contractor did not foresee. Beside it sits your own contingency, held outside the GMP for what you will ask for later. The two funds have different purposes, and different owners.

Every time something happens on site, someone decides which of the two funds pays. A duct that does not fit. A drawing that omitted a damper count. Rock under a pile cap. Each one is charged to one fund or the other, and the decision moves real money from one side of the contract to the other.

The party making that decision, in practice, is the contractor. The contingency log, the change order list and the pay application are all written by the contractor's project team, in the contractor's system, on the contractor's schedule.

You find out in a monthly summary, written by the same party that spends the money. There is no second set of figures to check it against. So you take the contractor's word for it, because there is nothing else to take.

Where the GMP sits today, from the product dashboard. Fictional project. The contractor's contingency is a line inside the cap. Yours is held outside it.

What it costs you today

Four things that go wrong quietly.

None of these shows up as a line in the pay application. Each one is a decision made without you, or a date that passed without anyone counting.

A contingency that empties before anyone notices.

The contractor's fund is reported as a percentage drawn. Sixty six percent sounds survivable. Empty in two months, with thirteen months of work left, does not. Once it is gone, events it would have absorbed arrive as owner change orders, and nobody announces the moment it happened. What happens after that.

A change billed as your scope when it was a design gap.

The cause written on a change order decides who pays. Owner scope is your money and adds to the GMP. A design gap is the contractor's fund under the contract. The same duct conflict can carry either label, and the label is assigned by the party that benefits from one of them.

A savings pool smaller than it should be.

Buyout below the GMP line builds a pool that the contract splits between you and the contractor. An overrun on one package reduces it, an allowance overrun reduces it, and an unclassified change parked as a design gap reduces it again. You see the pool at closeout, if then. Who owns the savings.

A notice deadline missed.

Most contracts give the owner a fixed number of days to respond to a claim or a change notice. The days are counted by nobody. A missed deadline weakens your position on that item, which is a money event, and it is recorded nowhere. The clock nobody is watching.

What this does about it

Your own ledger, written from your own documents.

The software applies rules and raises flags. It does not decide causes. People decide causes, and the ledger records who decided, when, and what it cost. You stop taking the contractor's word for it.

Two funds kept apart.

Contractor contingency and owner contingency are recorded on separate ledgers and charted against percent complete. The chart at the top of this page is that chart. A draw without a supporting document is flagged. The month the contractor's fund runs dry is stated as a month, not a percentage.

A cause on every change.

Owner scope, design gap, unforeseen condition, coordination, or unclassified. The cause decides which fund pays. Every change to a cause is written to an audit trail with a name and a timestamp. Items unclassified for more than thirty days are flagged until someone decides.

A savings pool you can check.

Each package carries its GMP line value next to its awarded value. The pool is the running difference, less booked overruns, split on the terms read from your contract at setup. A sensitivity table shows what the pool becomes if the open items land as owner scope, or as design gaps.

Deadlines counted in days.

Each change order carries its notice date, the contractual notice deadline, and the days remaining. A missed deadline is recorded as missed, with the item and the value it affects, so it is a known fact and not a surprise at closeout.

The change order register, as it renders in the product. Fictional project. A cause on every item, the age in days, and who pays once the cause is set. See all eight modules.

The work that disappears

The monthly report is generated, not assembled.

Today the owner's monthly position is built by hand. Someone opens the contractor's pay application, the contingency log and the change order list, copies the figures into a spreadsheet, reconciles the three against each other, and writes a narrative for the board or the lender. Next month it is done again from scratch, and last month's version is a file somewhere.

With a ledger of your own, the report is produced on the first of the month from what was already entered during the month. Twelve pages in a fixed order: cover, position summary, drawdown against progress, the change register with its cause split, open and unclassified items, buyout and the savings pool, allowance reconciliation, anticipated final cost, cash flow, shared savings, flags raised and closed, and what to decide before the next one.

What stops being manual: retyping figures from three sources, reconciling them against each other, comparing this month to last, and drawing the charts. What stays yours: the decisions. The report shows the facts in the same order every month, so the board reads the movement and not the formatting.

In the sample project on this page, five unclassified change orders carry $508,000. A year of the software costs $19,500.

Page 8 of the monthly owner report, as generated: anticipated final cost as a waterfall from the GMP. Fictional project. Inline SVG, so it prints the way it displays.

What it is not

It manages the inside of the GMP contract. Nothing else.

The distinction is the product. The development budget, the accounting system and the contractor's project management platform each have their own tool. This one has a narrower job and does not reach outside it.

Not accounting.

It does not post to a general ledger and does not replace one. It records what the contract says and what the draws show.

Not a payment system.

No money moves through it. Pay applications are read, not paid.

Not a replacement for Procore.

The contractor keeps its platform. The owner keeps a second ledger, written from the owner's documents.

Not a development budget tool.

Land, soft costs and financing live elsewhere. This covers the GMP line and what moves inside it.

The three ways owners do this today

A spreadsheet, the contractor's report, or Procore. What each one cannot do.

All three are reasonable tools. None of them is a second ledger. That is the gap this product fills, and nothing else.

The spreadsheet.

Free, flexible, and yours. Also retyped from three sources every month, reconciled by hand, and edited in place, so last month's figure is whatever the formula says today. There is no audit trail on a changed cell, and the whole thing leaves when its author does. The ledger keeps versions, stores monthly snapshots, and records who changed what.

The contractor's report.

Accurate on its own terms, and written by the party being paid. It shows the contingency as one number, the changes without a cause history, and the buyout when the contractor chooses to show it. Reading it is necessary. Checking it against your own record is the part that is missing, because there is no second record to check it against.

Procore.

The contractor's platform, and good at running the job. The owner reads what the contractor shares, in the contractor's structure, for as long as the contractor keeps the project open. It is the first ledger. It cannot also be the second one, and it does not carry the one field the owner needs most: who decided the cause, and when.

If a spreadsheet run by a person you trust is working for you, keep it. This exists for the owner who wants the record to outlive the spreadsheet and the summary to stop being the only source. Read how we work.

Pricing

Per active project. Never per seat.

An owner has two projects and fifteen people who need to read them. Charging per seat works against that, so every plan carries unlimited users. Monthly figures shown. Annual billing and the full comparison are on the pricing page.

Project
GMP $15 million to $50 million
$950
per project, per month
One time baseline setup $9,500
  • All eight modules
  • Unlimited users
  • Monthly owner report
Program
GMP $50 million to $150 million
$1,950
per project, per month
One time baseline setup $16,500
  • Everything in Project
  • Lender and investor guest access
  • Quarterly senior review call
Portfolio
GMP above $150 million, or several projects
$3,600
per project, per month
One time baseline setup from $24,000
  • Everything in Program
  • Portfolio view across owners
  • Named senior reviewer
GMP under $15 million? The baseline setup costs more than the exposure it protects on a contract that size. Use the free tools instead. They run the same engine.
Go to the free tools

Prices in US dollars. Advisory services, including the baseline setup done by a senior reviewer, are listed separately on the pricing page and are never bundled into a subscription.

One next step

See the ledger on a project like yours.

Thirty minutes on a call. We walk the eight modules on a fictional project at your GMP size, then show what the first monthly report would contain.

Request a demo